How to Write the Description of Work

Description of Work

Construction Equipment – Standard Plan Review

 

To facilitate review of your application and inspections of your project, please make sure that the description of work that you provide at the beginning of the application process is accurate, concise, and complete.

Requirements

For construction equipment the description must:

  • Describe scope of work, for example: “FOUNDATION FOR,” “PHASE 1,” or “PHASES 2-8”
  • Describe the type of equipment, for example: “TOWER CRANE,” “LUFFING CRANE,” or “CONSTRUCTION HOIST”
  • Identify the make and model of the equipment
  • Identify the permit number for earlier related permits

Examples

FOUNDATION FOR TOWER CRANE, CRANE UNDER SEPARATE PERMIT

INSTALL PHASE 1 TOWER CRANE (LIEBHERR 1234)

PHASE 2-4 TIE IN AND CLIMB SCHEDULE FOR TOWER CRANE INSTALLED UNDER PERMIT 100123456 (POTAIN ABC123)

INSTALL SINGLE-CAR RACK AND PINION CONSTRUCTION HOIST FOR MATERIAL ONLY WITH 2,600 LBS CAPACITY (HEK-1234S)