Construction Updates

This page is updated periodically with updates on the construction of the permanent casino.

November 2024: Demolition of existing buildings on the casino continues.

Aerial view of the demolition site, showing the demolition progress as of 11/13/2024.  The overall demolition is 52% complete, while the warehouse demolition is 63% complete.  The northwest section of the building that has been demolished is highlighted in red, and the section of the warehouse that has been demolished is highlighted in blue.

Continuing demolition of buildings on the casino site.

September 2024: Demolition of existing buildings on the casino site began.

Demolition of the buildings on the casino site. (Image 1)

Demolition of the buildings on the casino site. (Image 2)